Sembmarine Kakinada Limited (SKL) is developing a Dry Dock facility and proposed to construct dolphins and an approach platform to secure a steel floating dry dock.

It has two Dolphins of size 20.8X20.8m and an Approach platform of 37.6m Length and 12m width with Bored cast in-situ piles with Concrete Deck (+4.7m CD).

The Dolphin has to secure the floating dry dock on one side and allow berthing and mooring of vessels on the other side and an Approach Platform to provide access between NRW unit-1 and the nearest dolphin.